ANTICIPATED TO BEGIN: SUMMER 2017       

ANTICIPATED COMPLETION: EARLY 2018

PROJECT DESCRIPTION

The Sonoqui Wash channel will extend east from Ellsworth Road to the Crismon Road alignment.

STATUS UPDATE

The cultural resource evaluation to determine the extent of any artifacts is currently underway. The cultural resource evaluation is being completed because the channel passes through the Pozos de Sonoqui archaeological site.

UPCOMING MEETINGS

No meetings currently scheduled.

QC-Construction-Logo-Horiz-FINALFor more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.


 