Ellsworth and Queen Creek Road Intersection

Print
Press Enter to show all options, press Tab go to next option

CURRENT PHASE:  CONSTRUCTION OF PHASE 2

Work began in late February and scheduled for completion Spring 2019.

PROJECT DESCRIPTION

This project has been separated into two phases to accommodate the completion of construction during the school's summer break. Phase 1 construction is complete and consisted of improvements to Old Ellsworth Road from just north of the UPRR tracks to just south of Queen Creek Road. Improvements included street, drainage, sidewalk, landscape, street light and waterline improvements for construction of a cul-de-sac turnaround near the school/museum and realigning Walnut Road (Ellsworth Loop north connector) to provide for safer travel movements in the area. Phase 2 is currently under construction with the image below depicting the intersection configuration upon completion.

QC/Ellsworth Intersection

Phase 2 consists of the following improvements on Ellsworth Road from Walnut Road to Ryan Road and 1/8 mile east on Queen Creek Road:

  • Realignment and softening of the Ellsworth Loop/Ellsworth Road curve at the Queen Creek Road intersection to improve traffic flow and movement
  • Street improvements to widen Ellsworth Road to three lanes in each direction from Walnut to Ryan
  • Drainage, irrigation and waterline improvements
  • Sidewalk and landscape improvements
  • Traffic signal improvements  

CURRENT TRAFFIC IMPACT

Ellsworth Road from Walnut Road to Germann Road is shifted to the west side of Ellsworth Road, two lanes in each direction, with left turn restrictions in place north of Fulton Parkway to south of Germann, so that work can take place to construct the east side of Ellsworth Road.  In addition, speed limits are reduced to 35mph through this area.

The construction of this phase (Phase 2) has been broken into phases, as follows, with a tentative updated timeline for each below. Initial work is currently taking place off the roadway to work on traffic signals and placing temporary pavement on the shoulder to accommodate the traffic through the intersection during construction.

  • Phase 1/2 (Feb-Nov) – Underground of SRP electric, temporary asphalt on shoulders and traffic signal improvements - COMPLETE
  • Phase 3 (Dec-Jan) – Construct the northeast corner of the intersection - IN PROGRESS
  • Phase 4 (Dec-Jan) – Construct the southeast section of the intersection - IN PROGRESS
  • Phase 5 (Jan-Feb) – Construct the west side of Ellsworth Road in the project area
  • Phase 6 (Mar) – Work in the center of Ellsworth (half and half through the intersection) to install median islands
  • Phase 7 (Early Spring 2019) – Final paving and striping of the intersection

Please see the phasing graphics below for each of the phases which indicate where the construction zone will be and where travel will be shifted.  During construction, the contractor has phased traffic to maintain two lanes of travel in each direction on Ellsworth Road; however, in work efforts that require further restrictions, those will be scheduled during daytime off-peak hours to accommodate traffic on Ellsworth Road.    

In partnership with private development, work will concurrently be taking place on Ellsworth Road north of Queen Creek Road by private development to complete improvements to Ellsworth Road, ultimately providing three travel lanes in each direction with a center lane. 

Roads will remain open for travel during construction with speed limits reduced and traffic shifts in place shifting traffic away from the construction activity to maintain a safe work zone.

Ells QC - PH 1-2   Ells QC - PH 3-4

Ells QC - PH 5-6a   Ells QC - PH 6b-7 v2

STATUS UPDATE

Phase 3 and 4 of the work has begun with work taking place on the northeast corner of the intersection, and the southeast section as well. Ellsworth Road traffic is shifted to the west side of Ellsworth Road, providing for two lanes in each direction, with left turn restrictions in place near the work zone.

Construction is estimated to be complete Early Spring 2019.   

QC-Construction-Logo-Horiz-FINALFor more details about this project, please contact our project hotline at 480.898.4090.

For more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.


 

  

 

 

 

 

 

 