Show/Hide
For information about fishing, including licenses and stocking schedule, at Mansel Carter Oasis Park, please visit AZGFD.com.

Ellsworth and Queen Creek Road Intersection

Print
Press Enter to show all options, press Tab go to next option

CURRENT PHASE:  CONSTRUCTION OF PHASE 2

Work began in late February and scheduled for completion Early 2019.

PROJECT DESCRIPTION

This project has been separated into two phases to accommodate the completion of construction during the school's summer break. Phase 1 construction is complete and consisted of improvements to Old Ellsworth Road from just north of the UPRR tracks to just south of Queen Creek Road. Improvements included street, drainage, sidewalk, landscape, street light and waterline improvements for construction of a cul-de-sac turnaround near the school/museum and realigning Walnut Road (Ellsworth Loop north connector) to provide for safer travel movements in the area. Phase 2 is currently under construction with the image below depicting the intersection configuration upon completion.

QC/Ellsworth Intersection

Phase 2 consists of the following improvements on Ellsworth Road from Walnut Road to Ryan Road and 1/8 mile east on Queen Creek Road:

  • Realignment and softening of the Ellsworth Loop/Ellsworth Road curve at the Queen Creek Road intersection to improve traffic flow and movement
  • Street improvements to widen Ellsworth Road to three lanes in each direction from Walnut to Ryan
  • Drainage, irrigation and waterline improvements
  • Sidewalk and landscape improvements
  • Traffic signal improvements  

CURRENT TRAFFIC IMPACT

Ellsworth Road Northbound and Southbound lane shift between Fulton Pkwy and Germann Road AND Eastbound and Westbound lane shifts and turn lane restrictions at German Road and Ellsworth Road intersection for irrigation install. Jul. 22 – Jul. 27; 8 pm – 5 am

The construction has been broken into phases, as follows, with a tentative timeline for each. Initial work is currently taking place off the roadway to work on traffic signals and placing temporary pavement on the shoulder to accommodate the traffic through the intersection during construction.

  • Phase 1/2 (Feb-Aug) – Underground of SRP electric, temporary asphalt on shoulders and traffic signal improvements
  • Phase 3 (Aug-Sep) – Construct the northeast corner of the intersection
  • Phase 4 (Sep-Octg) – Construct the southeast section of the intersection
  • Phase 5 (Oct-Dec) – Construct the west side of Ellsworth Road in the project area
  • Phase 6 (Dec) – Work in the center of Ellsworth (half and half through the intersection) to install median islands
  • Phase 7 (Early 2019) – Final paving and striping of the intersection

Please see the phasing graphics below for each of the phases which indicate where the construction zone will be and where travel will be shifted.  During construction, the contractor has phased traffic to maintain two lanes of travel in each direction on Ellsworth Road; however, in work efforts that require further restrictions, those will be scheduled during daytime off-peak hours to accommodate traffic on Ellsworth Road.    

In partnership with private development, work will concurrently be taking place on Ellsworth Road north of Queen Creek Road by private development to complete improvements to Ellsworth Road, ultimately providing three travel lanes in each direction with a center lane. 

Roads will remain open for travel during construction with speed limits reduced and traffic shifts in place shifting traffic away from the construction activity to maintain a safe work zone.

Ells QC - PH 1-2   Ells QC - PH 3-4

Ells QC - PH 5-6a   Ells QC - PH 6b-7 v2

STATUS UPDATE

Phase 2 construction has begun, with initial work taking place off the roadway to work on traffic signals and placing temporary pavement on the shoulder to accommodate the traffic through the intersection during construction.

Overhead electric conversion to underground remains underway.  SRP has been pulling cable and wiring as weather permits.  Median removal and temporary pavement work occurred to permit traffic shifting for adjacent work.   Staff and the Construction Manager at Risk (CMAR) contractor continues to coordinate with the adjacent four developers to move the electric utility conversion and Ellsworth Road improvements forward.  Irrigation tie-in work from Ryan Road to Germann will impact Ellsworth Road in the coming month.

Construction is estimated to be complete Early 2019.   

QC-Construction-Logo-Horiz-FINALFor more details about this project, please contact our project hotline at 480.898.4090.

For more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.


 

  

 

 

 

 

 

 

Save