Trash and recycling services will be impacted for residents in Zone 3 on Thanksgiving Day; services will be delayed until Friday. Residents will need to have their carts out by 6 a.m. on Friday, Nov. 29 for service. As a reminder, residents may schedule bulk trash services online at QueenCreek.org/BulkTrash.

Meridian Road - Combs to Germann Roads

Print
Press Enter to show all options, press Tab go to next option

CURRENT STAGE: DESIGN

Scheduled Design Phase: 2019-2020

Scheduled Construction Phase: 2020-2021

A1505-Meridian Road Overall Map - WebsiteRevised_Reduced

PROJECT DESCRIPTION

This joint project with Pinal County consists of design and construction of various half street improvement segments and a full street width multi-barrel culvert crossing of Queen Creek Wash to include paving, curb and gutter, sidewalks, drainage, traffic signals and street lights. Adjacent development will build the other half street as it occurs.

CURRENT TRAFFIC IMPACT

None at this time.

STATUS UPDATE

Expedited design of the Queen Creek Wash crossing and temporary roadway from Combs Road to the Queen Creek Wash has reached 90% development, and is under agency review.  Western half street improvements from Combs Road to Queen Creek Wash and Queen Creek Road to Germann Road are scheduled to reach 60% level of design in the spring of 2020.

MEETING SCHEDULE: 

No meetings currently scheduled.

 


For more details about this project, please contact our project hotline at 480.898.4090.

For more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.