Meridian Road - Combs Road to Germann Road

Print
Press Enter to show all options, press Tab go to next option

CURRENT STAGE: DESIGN

Scheduled Design Phase: 2019-2020

Scheduled Construction Phase: 2020-2021

 A1505-Meridian Road - Groundbreaking- Exhibit 2

PROJECT DESCRIPTION

This joint project with Pinal County consists of design and construction of various half street improvement segments and a full street width multi-barrel culvert crossing of Queen Creek Wash to include paving, curb and gutter, sidewalks, drainage, traffic signals and street lights. Adjacent development will build the other half street as it occurs.

This project has been divided into the following phases:

Phase 1 – Queen Creek Wash Crossing and Temporary Road: This phase will expedite the completion of the ultimate Queen Creek Wash crossing of Meridian Road, and provide temporary pavement for a traffic connection between Combs Road and the existing roadway at Cherrywood Drive in Church Farms. This portion of the project will start construction near the end of 2019, and is scheduled for completion by Spring of 2020.

Phase 2 – Combs Road to Cherrywood Drive West Half Street: This phase will complete the western half street from Combs Road to the existing roadway at Cherrywood Drive in Church Farms. Future development will complete the other half street at a later date as it occures. This phase is projected to start construction Summer of 2020.

Phase 3 – Queen Creek Road to Germann Road West Half Street: This phase will complete western half street improvements from Queen Creek Road to Germann Road. A separate Town project will continue half street improvements from Germann Road to the future State Route 24. This phase is projected to start construction Fall of 2020.

CURRENT TRAFFIC IMPACT

None at this time.

STATUS UPDATE

Phase 1 - Queen Creek Wash Crossing and Temporary Road:

A Ground breaking ceremony was held on December 3, 2019.  Construction is underway with clearing, surveying and some subgrade preparation scheduled for completion by the end of December.  Waterline and box culvert cutoff wall excavations are underway.

Phase 2 - Combs Road to Cherrywood Drive:

Western half-street improvements are progressing towards the 60% design stage.  Utility coordination efforts are underway.  The 60% design plan submittal is anticipated for early 2020.

Phase 3 - Queen Creek Road to Germann Road:

Preliminary drainage and roadway design is underway with 30% design anticipated for the end of 2019 or the first of 2020.

MEETING SCHEDULE: 

No meetings currently scheduled.

 


For more details about this project, please contact our project hotline at 480.898.4090.

For more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.