Ocotillo Road - Hawes Road to Sossaman Road

Print
Press Enter to show all options, press Tab go to next option

CURRENT STAGE: DESIGN

Scheduled Design Phase: 2018 - Early 2020

Construction Start: Early 2020

A0116_2018-1219_Ocotillo hawesToSossaman_Roll Plot1

PROJECT DESCRIPTION

The project consists of design and construction to widen Ocotillo Road to two lanes in each direction with a middle turn lane resulting in full street improvements with curb and gutter, bike lanes, sidewalk, drainage, irrigation, traffic signal and street light improvements.  Project limits include half street improvements south along the east side of Sossaman Road about 1,000 feet and north along Hawes Road about 800 feet.

The Town is assessing a possibility to divide the construction into two phases.  This staging could help reduce traffic impacts in the area due to other construction that will be occurring on Power Road and Chandler Heights Road on a similar schedule.

CURRENT TRAFFIC IMPACT

None at this time.

STATUS UPDATE

Design is progressing towards the 90% stage with plan submittal anticipated in early February.  Potholing for utility conflicts are underway.  Discussions regarding access continues with property owners.

MEETING SCHEDULE

No meetings currently scheduled.

 


For more details about this project, please contact our project hotline at 480.898.4090.


For more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.