Ocotillo Road - Signal Butte Road to Ironwood Road

Print
Press Enter to show all options, press Tab go to next option

CURRENT PHASE: DESIGN

Anticipated design phase: 2018-2019

Anticipated construction phase: Early 2020

A0115 OCOTILLO - SIGNAL BUTTE TO IRONWOOD RD

PROJECT DESCRIPTION

The project consists of design and construction to complete half street paving, curb and gutter, bike lanes, sidewalks, drainage, intersection and street light improvements. Development will build or has built the other half.

CURRENT TRAFFIC IMPACT

None at this time.

STATUS UPDATE

Design is progressing towards the 90% stage with plan submittal anticipated mid-February. Drainage and right-of-way discussions continues with property owners..

MEETING SCHEDULE

No meetings currently scheduled.

 


For more details about this project, please contact our project hotline at 480.898.4090.