Queen Creek Road and Signal Butte Road Intersection

Print
Press Enter to show all options, press Tab go to next option

CURRENT STAGE: DESIGN

Anticipated design phase:  Fall 2018 - Late 2019

Anticipated construction start: Early 2020

A1002-Ph1_Queen Creek - Signal Butte Intersection Exhibit_2019-0114_Page_1

PROJECT DESCRIPTION

The project will consist of design and construction of two travel lanes in either direction (north/south and east/west). This is the ultimate build out for the intersection with a traffic signal and street lights.

CURRENT TRAFFIC IMPACT

None at this time.

STATUS UPDATE

Development of project technical specifications and provisions are underway with bid advertising scheduled for mid-January.  Finalization of utility relocation plans by SRP and Queen Creek Irrigation District continues.

MEETING SCHEDULE

No meetings currently scheduled.

 


For more details about this project, please contact our project hotline at 480.898.4090.

For more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.