Trash and recycling services will be impacted for residents in Zone 3 on Thanksgiving Day; services will be delayed until Friday. Residents will need to have their carts out by 6 a.m. on Friday, Nov. 29 for service. As a reminder, residents may schedule bulk trash services online at QueenCreek.org/BulkTrash.

Rittenhouse Road - 213th Street to Riggs Road

Print
Press Enter to show all options, press Tab go to next option

CURRENT STAGE: DESIGN 

Anticipated design phase: Completed

Anticipated construction phase: Mid 2019-2020

A0306_Rittenhouse_213th to Riggs_Exhibit 2018-1020

PROJECT DESCRIPTION

The project consists of design and construction to widen Rittenhouse Road from the 213th Street alignment to Riggs Road. The project will provide two traffic lanes in each direction, median turn lanes at intersections and bike lanes. Construction will include the MCDOT designed replacement at Queen Creek Wash (TT430).  Improvements will include roadway replacement, curb and gutter, sidewalk, drainage, street lighting, and traffic signal upgrades.

CURRENT TRAFFIC IMPACT

None at this time.

STATUS UPDATE

Design is completed.  Bids for the roadway improvements are due September 2019.  A kick-off meeting was conducted with the Construction Management at Risk (CMAR) contractor to discuss the Rittenhouse Road bridge project schedule and formally request a cost proposal for the overall replacement.

Construction is estimated to be complete March 2020.

MEETING SCHEDULE

No meetings currently scheduled.

 


For more details about this project, please contact our project hotline at 480.898.4090.

For more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.